Capex edges higher in Iamgold’s latest update for Cote gold project in Ontario

Date:

Estimated operating costs also went up to C$854 ($665) per oz. of gold sold, from C$802 ($624) per oz. in its 2021 technical report.  

In 2020, before construction began, Iamgold pegged its 70% of costs at $875-$925 million (which would put total costs at around $1.3 billion). 

Côté’s mine life is estimated to be 18 years, with initial production now pushed ahead to early 2024 from the previous schedule of late 2023. The project is located about 125 km southwest of Timmins. 
 
Iamgold interim CEO Maryse Bélanger said the company is pursuing alternatives to increase liquidity to complete construction and start production in line with the updated schedule. 
 
“We expect to address these near-term challenges to advance Côté and better position Iamgold as a more resilient, agile company for the current environment,” she said. 
 
The expenditure increase comes after the company’s previous assessment in January put…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...