Taseko’s Florence copper project almost 40% complete

Date:

Taseko’s focus has been on earthworks, concrete pouring, and wellfield drilling, achieving new milestones, such as the installation of structural steel and process equipment.

“With approximately 75% of total construction costs now committed, we expect total costs to be within 10-15% of the original $232 million estimate,” president and chief executive Stuart McDonald said in the update.

Getting to this point hasn’t been easy. Taseko faced initial opposition and legal challenges over fears of the mine’s environmental impact.

The US Environmental Protection Agency cleared the way in November last year, issuing the final permit required to begin construction at Florence.

Shortly after, Taseko secured additional fundings totalling $100 million for the proposed copper mine, supplementing the previous financings from its partner Mitsui as well as Bank of America.

Source: Taseko’s presentation, Oct. 2024.

When fully…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...