Seabridge Gold’s KSM project going greener

Date:

Seabridge had originally planned to use diesel power during construction, with hydro power incorporated later from BC Hydro’s Northwest Transmission Line (NTL) for operations.

KSM will now connect to NTL at BC Hydro’s Treaty Creek Switching Station (TCT), currently under construction, but expected to be completed before the end of 2024.

“Having access to low-cost hydro power is one of many logistical advantages KSM enjoys compared to other large undeveloped gold and copper projects around the world,” CEO Rudi Fronk said in the statement.

The cost of the new BC Hydro switching station is $28.9 million in cash payments for facilities directly required by the KSM project and $54.2 million in security (or cash in lieu) for BC Hydro system reinforcement as required to make the power available, the miner said.

Seabridge has completed its design for a 30 km long 287 KV transmission line to interconnect the TCT and the KSM plant…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...