Robex Resources (TSXV: RBX) said on Wednesday it remains on track to deliver first gold from its Kiniero project in Guinea by the end of this year. Shares of the West Africa-focused gold developer surged on the update.
In a press release, Robex said construction of the Kiniero mine continues to track well against the schedule, with the SAG and ball mill foundation already completed. The primary crusher ROM (run of mine) wall is also complete; backfilling of the ROM pad is now underway.
The company added that structural steel and platework fabrication is over halfway complete at 55%, while concrete work for the process plant is progressing on schedule, with 85% poured. The tank structures are almost halfway complete (42%).
Given the progress to date, Robex said it is well-positioned to advance the Kiniero project towards production by the fourth quarter of 2025. Production for 2026 is expected to reach…