TORONTO, ON / ACCESS Newswire / August 27, 2025 / PPX Mining Corp. (TSX.V:PPX) (BVL:PPX) (the “Company” or “PPX”) is pleased to provide an update on the progress of its plant construction activities at its Igor Project in northern Peru.
On August 25, PPX commenced the installation of the metal-mechanical equipment purchased from Xinhai. This first stage of assembly is expected to take approximately two months. Work has begun on the installation of equipment in the crushing and milling areas, as well as the preparation of the first conveyor belts.
Current activities include:
– Installation of the jaw crusher
– Installation of gear motors and bases for the ball mill
-Installation and alignment of the sole plates for the ball mill trunnions
– Installation of feed boxes and spout feeders for the 7’x12′ mills
– Placement of impact idlers and guides in conveyor belt structures
The following images illustrate the on-site progress of…