TORONTO, ON / ACCESSWIRE / November 14, 2024 / PPX Mining Corp. (the “Company” or “PPX“, including its Peruvian subsidiaries) is pleased to announce that construction of the CIL and Flotation plant at its Igor Project located in La Libertad, Peru, has started.
Yesterday, major components for the plant were ordered and are described as follows:
-
Equipment for the crushing circuit, which includes primary jaw crusher, secondary cone crusher, vibrating screen and all conveyors.
-
Equipment for the grinding circuit, which includes two ball mills, hydro-cyclones, pumps and a thickener.
-
Equipment for the flotation circuit, which includes flotation cells, concentrate thickener and filter press.
Equipment for the leaching equipment is in the process of being ordered.
Additional detailed engineering has also begun, with a final review of the entire layout and geotechnical data, to be completed in the coming weeks by the EPC…