Equinox Gold’s Greenstone mine reaches commercial production

Date:

“This milestone marks the culmination of three years of construction and commissioning, accomplished during the challenges of a global pandemic, supply chain disruptions and inflationary pressures,” Equinox CEO Greg Smith said in a Nov. 6 news release.

At full production, Greenstone will be one of Canada’s largest and highest-grade open-pit gold mines, producing on average 390,000 oz. of gold per year for the first five years and 330,000 oz. of gold annually for an initial 15-year mine life.

Lowered 2024 guidance

Initially, Greenstone’s 2024 gold production was forecasted at 175,000-205,000 oz., with Equinox targeting 90% of the 27,000 tonne-per-day plant capacity by year-end.

However, during the third quarter, the mine had been processing ore at only 53% of the design throughput (14,3000 t/d) due to three multi-day shutdowns to address issues identified in the ramp-up process. The resulting quarterly…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...