Equinox Gold says Greenstone project is full steam ahead

Date:

Inflationary pressures have been mitigated through offsetting savings opportunities or absorbed through the C$177 million contingency included in the construction budget, the company adds.

So far, locations on site such as the Ministry of Transportation (MTO) patrol yard, the Goldfield Creek diversion and the permanent effluent water treatment plant have already been completed. The first four bays of the truck shop are complete and in use and the 14 km natural gas pipeline is complete and ready for commissioning in second quarter of 2023.

Pre-production mining also commenced ahead of schedule, as first four haul trucks and the first shovel were commissioned during the third quarter of 2022 and mine pre-production activities got underway in September, with more than 2.5 million tonnes of material (ore, waste and overburden) excavated to year-end 2022.

“With key equipment on site or enroute, building infrastructure is essentially…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...