Bunker Hill Mining Provides Project Restart Update February 2024

Date:

Early 2024 milestones

  • Arrival of mill and other key components from the shuttered Golden Sunlight mine brings the procurement of Processing Plant equipment past the 80% threshold.
  • Power cables and infrastructure have now been ‘dropped’ underground, bringing all parts of the mine – surface and subsurface – onto low-cost, hydroelectric-dominated mainline electric grid power.
  • Drilling contract for resource definition and expansion to commence in Q2 2024 has been awarded to Dynamic Drilling, Inc. of Osburn, ID.

Remaining Q1 2024 events

  • Demolition of the old mining offices to create space for a new, purpose-built Filtration Plant is underway and due to complete by the end of Q1 2024.
  • LFI of Hutchinson, KS is due to deploy in early March to commence drilling of auger-cast piles as part of the pre-foundation work for the Process Plant and Filtration Plant buildings.

PDAC Conference – Metro Toronto Conference Centre (3-6 March 2024)

  • Bunker…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...