Early 2024 milestones
- Arrival of mill and other key components from the shuttered Golden Sunlight mine brings the procurement of Processing Plant equipment past the 80% threshold.
- Power cables and infrastructure have now been ‘dropped’ underground, bringing all parts of the mine – surface and subsurface – onto low-cost, hydroelectric-dominated mainline electric grid power.
- Drilling contract for resource definition and expansion to commence in Q2 2024 has been awarded to Dynamic Drilling, Inc. of Osburn, ID.
Remaining Q1 2024 events
- Demolition of the old mining offices to create space for a new, purpose-built Filtration Plant is underway and due to complete by the end of Q1 2024.
- LFI of Hutchinson, KS is due to deploy in early March to commence drilling of auger-cast piles as part of the pre-foundation work for the Process Plant and Filtration Plant buildings.
PDAC Conference – Metro Toronto Conference Centre (3-6 March 2024)
- Bunker…