The Airstrip deposit was delineated by 139 drill holes by mid-May last year. The bulk of the gold identified is hosted within a calcareous package, a roughly 90-metre-thick east-west striking zone. There are 35.2 million inferred tonnes grading 0.746 g/t gold and containing 845,276 oz. with a 0.3 g/t cut-off.
The Powerline deposit was tested with 954 holes in the last year. The mineralization model is comprised of eight parallel and undulating mineralized zones. The bulk of the resource is hosted in quartz veins. The total inferred resource (using a 0.3 g/t gold cut-off) is 312.2 million tonnes grading 0.613 g/t gold and containing 6.2 million oz.
“Metallurgical studies to date have demonstrated that Powerline mineralization is amenable to conventional mining processes, including carbon-in-pulp and carbon-in-leach, flotation and heap leaching,” said president and CEO Tara Christie.
“Looking at the grade sensitivities, at a…