MONTREAL, June 26, 2024 (GLOBE NEWSWIRE) — Aya Gold & Silver Inc. (TSX: AYA; OTCQX: AYASF) (“Aya” or the “Corporation”) is pleased to announce the beginning of commissioning activities at its new 2,000 tonnes per day (“tpd”) mill at the Zgounder Silver Mine in the Kingdom of Morocco.
- Highlights
- Zgounder expansion over 95% complete.
- Pre-commissioning activities are ongoing in the main process plant areas, including the grinding circuit and the silver refinery as part of the commissioning process:
- Tests are being conducted on the ball mill, which is running without loads
- Energization of the silver furnace and systems checks completed
- The conveyors have been energized and tested
- The retort and ventilation have been energized
- Pre-commissioning of the renewable-energy power line is near-complete for energization in the coming days.
- Operations commissioning team is fully mobilised and readiness activities…