The signed document establishes a workplan for all parties to collaborate on an efficient Environmental Assessment (EA) and permitting process for Eskay Creek. The target timelines established in the Process Charter outline the EA Certificate being received in H2 2024 and final permits to be issued in H1 2025. These dates align with the development timeline anticipated for the project.
“The TCG recently finalized the Process Charter for Eskay Creek,” Connor Pritty, TCG Lands Director said in a news release. “It is an example of how Skeena is continually working with the Tahltan Nation to redefine how project approval processes are carried out within our Territory.
“We are working together to effectively integrate Tahltan knowledge, process requirements and decision-making specific to Eskay Creek,” Pritty said. “The TCG Lands Department looks forward to continuing to work with the team at Skeena.”
“The Process…