SilverCrest begins commissioning Las Chispas in Mexico

Date:

It added it expects a more measured ramp-up of underground mining and increased operational flexibility over the first few years of production due to a significant amount of stockpiled ore.

“I would like to thank the combined team of Ausenco and SilverCrest for their continued efforts over the past 17 months, SilverCrest COO Pierre Beaudoin said in the statement.

“Completing construction during the covid-19 pandemic has tested everyone’s resilience and it is with great satisfaction that I congratulate them for accomplishing an incredible trio of successes: No major accidents, below budget and ahead of schedule.”

The company highlighted it expects the capital cost of Las Chispas to be lower than the $137.7 million budgeted in the feasibility study but said final costs of the project remain to be settled.

Las Chispas is expected to produce 12.4 million ounces a year of silver equivalent between 2023-2029 from a 1,250 tonne…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...