Aris Mining Announces Steady Ramp-Up at Segovia Following Second Mill Commissioning in Late June

Date:

VANCOUVER, BC, Sept. 5, 2025 /CNW/ – Aris Mining Corporation (Aris Mining or the Company) (TSX: ARIS) (NYSE-A: ARMN) reports strong progress with the ramp-up at its Segovia Operations following successful commissioning of a second mill in June 2025. The expanded processing capacity has already delivered a substantial increase in mill throughput and gold production.

Key highlights:

  • The second mill was successfully commissioned in late June 2025, on time and within budget, increasing installed processing capacity by 50% from 2,000 tonnes per day (tpd) to 3,000 tpd.
  • Milling rates increased sharply in July and August, averaging 2,415 tpd, compared to 1,971 tpd over the six months ended June 30, 2025. In August, throughput also reached approximately 3,000 tpd on several days, demonstrating strong operating performance at design capacity.
  • Processed gold grades averaged 10.02 g/t Au in July and August, which reflects disciplined…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...