PPX Mining Update on Equipment Installation at Site

Date:

TORONTO, ON / ACCESS Newswire / August 27, 2025 / PPX Mining Corp. (TSX.V:PPX) (BVL:PPX) (the “Company” or “PPX”) is pleased to provide an update on the progress of its plant construction activities at its Igor Project in northern Peru.

On August 25, PPX commenced the installation of the metal-mechanical equipment purchased from Xinhai. This first stage of assembly is expected to take approximately two months. Work has begun on the installation of equipment in the crushing and milling areas, as well as the preparation of the first conveyor belts.

Current activities include:

– Installation of the jaw crusher

– Installation of gear motors and bases for the ball mill

-Installation and alignment of the sole plates for the ball mill trunnions

– Installation of feed boxes and spout feeders for the 7’x12′ mills

– Placement of impact idlers and guides in conveyor belt structures

The following images illustrate the on-site progress of…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...