Taseko’s Florence copper project 90% complete

Date:

Taseko Mines (NYSE: TGB; TSX: TKO) reported that construction of its Florence Copper mine in Arizona is now over 90% complete.

The company confirmed the project remains on track to produce first copper cathode by the end of 2025. The operation is projected to boost Taseko’s copper production by 120%, based on a 2024 guidance of 110 million-115 million pounds of the metal.

Source: Taseko’s presentation, Oct. 2024.

Taseko said that more than 900,000 hours of project work have been completed with no reportable injuries or environmental incidents to date, and the workforce has tapered to roughly 330 on-site personnel.

All planned injection and recovery wells have been drilled, and the 69 kV substation has been energized, marking a significant milestone in the ramp‑up process.

Shares of Taseko rose 1% on Tuesday, putting the company’s market capitalization at approximately…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...