Study reveals renewable energy project lead-times

Date:

Credit: Pixabay/CC0 Public Domain

Western Sydney University has released new research assessing how long it takes to get renewable energy projects planned, approved, built, and commissioned.

Published in Energy Economics, the study investigated the factors determining lead-times for 170 onshore wind and solar photovoltaic (PV) projects completed in Australia between 2000 and 2023.

It found a notable improvement in lead-times for onshore wind and solar projects. However, the study also found that commissioning lead-times, the final step of the process, have increased for solar…

Read more…

Share post:

Subscribe

spot_imgspot_img

Popular

More like this
Related

Tampa RV giant Lazydays to delist from Nasdaq

Tampa-based Lazydays Holdings Inc., one of Florida’s most recognized...

Granite Geek: New Hampshire might get access to ‘balcony solar’

I had solar panels put on my roof six...

TSX Today: What to Watch for in Stocks on Monday, November 10

Despite firm gold and silver prices, Canadian stocks...

While BNB and DOT Struggle Under Market Pressure, BlockDAG’s Presale Soars Past $435M!

As market-wide fear grips the sector, the Binance Coin...